Underwriting Manual: DC

12.12.17

Mechanic's Liens

  • No references available.
  • No references available.
State Supplements

View state supplements to the national underwriting manual.

  • Download
  • Download .pdf
  • Download .doc
V 3

Mechanic’s Lien Coverage Requires Underwriter Approval.

Priority

Can the Construction Loan Mortgage have initial priority over mechanic's liens?

Advances/draws made under a construction loan mortgage can have priority over a mechanic’s lien if at the time of the advance/draw a Notice of Intent (notice of mechanic’s lien) has not been filed in the land records. See code § 40–301.02 and § 40–303.07

Will initial priority as to future disbursements be retained only if certain procedures are followed?

The priority as to future disbursements will be retained, as long as a Notice of Intent has not been filed in the land records. 

If priority is lost, can it be regained?

If priority was established but has now been compromised due to the filing of a Notice of Intent or an action to enforce a mechanic’s lien, priority may be regained if the lien is satisfied, payment is made to the court in the amount claimed by the lienor, or a bond is posted that would cover the amount of said lien. See § 40–303.15 and § 40–303.16

Is there a difference between on-site and off-site work?

DC’s mechanic’s lien statute does not differentiate between on-site and off-site work. Therefore, any work completed, regardless of location, would be eligible to be claimed in the Notice of Intent.

Is priority the same for all contractors and subcontractors on the same project?

A subcontractor’s mechanic’s lien will have priority over the lien of the general contractor for the project.

Subcontractors, materialman etc. hired to complete a project will also have the same rights as the original subcontractor, materialman, etc. on that project. If there are competing mechanic’s liens on a project, all subcontractor claims are given equal priority and will be paid their pro-rata share in a case where there are insufficient funds to cover all claims. See § 40-303.10 § 40-303.11

Time Limits

What are the time periods for recording lien claims by original contractors and subcontractors?

The Notice of Intent shall be recorded during the construction or within 90 days after the earlier of the completion or termination of the project. If the Notice of Intent is not recorded in the land records during this timeframe, the contractor’s lien rights are terminated. See § 40–301.02

After what period of time can you waive a mechanic's lien if no suit is filed?

Within 180 days after the recording of the Notice of Intent, a legal action must be initiated to enforce the lien. Failure to file an action within the 180-day timeframe shall terminate the right to establish a lien, see § 40–303.08 and § 40–303.13

Removing or Waiving Liens

Is there a statutory procedure for affidavits of completion or notices of completion?

No.

Can a statutory bond terminate the mechanic's lien as an encumbrance on the title?

Yes, the owner may pay into court the amount claimed by the lienor, and such additional amount, to cover interest and costs, as the court may direct; or file a written undertaking (bond), with one or more sureties, to be approved by the court, with the effect to pay the judgment that may be recovered. This will allow the owner to release the property from the lien while the dispute is ongoing. See § 40–303.16

Can the original, general, or subcontractor's contract or waiver agreement subordinate or waive mechanic's liens by general contractor and/or subcontractors?

A general contractor may waive their right to a lien in their contract with the owner, but the general contractor cannot bind a subcontractor.  DC Code protects subcontractors' lien rights by preventing a general contractor from waiving them on their behalf. See § 40–303.02

Can a bona fide purchaser or bona fide lender take free of mechanic's liens later filed for earlier work?

Generally, no. The only exceptions are a mortgage given to secure the purchase of a property, which is recorded within 10 days from the date of the last acknowledgment, and any construction advances that are made prior to the recordation of the Notice of Intent, see § 40–303.07

 

Title Company Requirements

What are the customary requirements for issuing Loan Policies on construction loan mortgages?

The issuing office must provide the draw schedule, the construction budget, the sources and uses statement and provide signed mechanic’s lien indemnities, waivers and affidavits, as applicable, to the underwriter for review. Furthermore, the issuing office will need to know if construction has started and the amount of the initial draw.

 

Is it customary to add a "pending disbursement" clause or mechanic's lien exception in the Loan Policy insuring a construction loan mortgage?

Yes. The following pending disbursement clause is commonly used in Commitments and lender policies on construction loans: “Pending disbursement of the full proceeds of the loan secured by the Deed of Trust referred to in Schedule A hereof, this Policy insures the insured only to the extent of the funds actually disbursed but shall increase as subsequent disbursements are made by the insured on good faith and without knowledge of any defects in or objections to title, up to the Amount of Policy stated in Schedule A provided that prior to or at the time of each such disbursement the title shall be continued down to such time and any liens and other objections to title which may have arisen between the Date of Policy and the date of such disbursement shall be added to Schedule B hereof.”

Also subject to any bulletins relating to mechanic's liens.

Updated June 11, 2025

  • Download
  • Download .pdf
  • Download .doc